Iran said yesterday that the Russian contractor of its Bushehr nuclear power
plant was facing financial problem, but stressed that both sides were still
working to finalize the project on schedule, the official IRNA news agency
reported.
Gholam-Reza Aqazadeh, head of Iran's Atomic Energy Organization, made the
remarks at a joint press conference with his visiting Russian counterpart Sergei
Kiriyenko.
Admitting the financial difficulties facing the nuclear power plant project,
Aqazadeh still stressed the importance of cooperation between the two sides for
the timely implementation of the project.
Moscow is due to complete Iran's long-delayed first nuclear power station in
September 2007 and deliver the nuclear fuel by the end of the current Iranian
year, which ends on March 20, 2007.
When asked whether the required nuclear fuel could be sent to Iran on time,
Aqazadeh said that the schedule had not changed.
For his part, Kiriyenko said that some progress had been made in the
implementation of the project, but outspoke that "it is not sufficient".
Iranian and Russian experts were required to further exchange their views in
a bid to expedite the project, he added. According to Aqazadeh, the Russian
contractor expected Iran to provide financial aid beyond the initial agreement.
In addition to financial difficulties, the failure in the delivery of premade
equipment by third-party countries was another problem facing the Bushehr
project, Kiriyenko said.
According to Iran's Mehr news agency, Aqazadeh said that Iran had decided to
provide assistance beyond previous agreements to Russia in order to solve the
technical problems of the power plant.
But Mohammad Saeedi, deputy chief of Iran's Atomic Energy Organization for
international and planning affairs, made it clear that "Iran will not pay Russia
more than what has been agreed."
Iran only decided to speed up the payments in order to accelerate the
construction of the power plant, said Saeedi.
Moreover, "if the third-party countries do not send the equipment required
for the power plant, it will be built in Russia and sent to Tehran," Saeedi was
quoted as saying.
Iran signed up Russian nuclear industry construction firm Atomstroi export in
1995 to build the Bushehr plant for a contract worth about 1 billion U.S.
dollars.
The Russians began building Bushehr in 1998. The Bushehr plant was previously
scheduled to become operational by the end of 2006.